Reserved Amount = € 0,00 € 83.355,00
100% Funded
8 yr
term
4.47%
a year
monthly
instalment
B+
rating

Sustainable energy

SDG 11. Sustainable Cities and Communities
PV plant for self-consumption with 94kWp
Impact
The estimated anual production is 147 MWh of clean energy, avoiding the emission of around 40 tons of CO2 – the equivalent of 957 Lisboa-Porto car trips. Moreover, this project will allow Gabrimat to become less dependent on the energy prices rise, therefore becoming more competitive.
Project Information
Gabrimat is a family company dedicated to industrial casting in the region of Leiria. Founded in 1990 and in its 2nd generation, the company is increasingly concerned about energy and resources efficiency.The project aims to install photovoltaic solar panels for the factory’s self-consumption with 94 kWp of installed capacity. Financing target is equal to 83355,00€.
Attached Documents
100% Funded
8 yr
term
4.47%
a year
monthly
instalment
B+
rating

Sustainable energy

SDG 11. Sustainable Cities and Communities
PV plant for self-consumption with 94kWp
Reserved Amount = € 0,00 € 83.355,00
Impact
The estimated anual production is 147 MWh of clean energy, avoiding the emission of around 40 tons of CO2 – the equivalent of 957 Lisboa-Porto car trips. Moreover, this project will allow Gabrimat to become less dependent on the energy prices rise, therefore becoming more competitive.
Project Information
Gabrimat is a family company dedicated to industrial casting in the region of Leiria. Founded in 1990 and in its 2nd generation, the company is increasingly concerned about energy and resources efficiency.The project aims to install photovoltaic solar panels for the factory’s self-consumption with 94 kWp of installed capacity. Financing target is equal to 83355,00€.
Attached Documents
Gabrimat, Lda
About Gabrimat, Lda
Gabrimat LDA is a family company dedicated to industrial casting in the region of Leiria. Founded in 1990, mainly produces for the areas of sanitation, gymnastics and public lighting. In its 2nd generation, the company has adopted a more sustainable path to make the production process more circular and energy efficient. Thus, Gabrimat has already adopted a zero-waste policy, recycling and integrating all the defective products into a new production cycle. Furthermore, has also changed the lightning use in the facilities to LED.
The Business Model
This project being an installation for self-consumption, it will create direct savings on Gabrimat electricity consumption. Adding to this, the production surplus will be sold to the grid. These monthly savings on their electricity bill are enough to cover the financial obligations to the investors and GoParity, making this a sustainable project, not only for the environment but also financially.
Track Record
Gabrimat is a family company dedicated to industrial casting in the region of Leiria. Founded in 1990, mainly produces for the areas of sanitation, gymnastics and public lighting.
Promoter Rating: B+
Guarantees
This loan is secured with the pledge of the equipment.
Gabrimat, Lda
About Gabrimat, Lda
The Business Model
This project being an installation for self-consumption, it will create direct savings on Gabrimat electricity consumption. Adding to this, the production surplus will be sold to the grid. These monthly savings on their electricity bill are enough to cover the financial obligations to the investors and GoParity, making this a sustainable project, not only for the environment but also financially.
Track Record
Gabrimat is a family company dedicated to industrial casting in the region of Leiria. Founded in 1990, mainly produces for the areas of sanitation, gymnastics and public lighting.
Promoter Rating: B+
Guarantees
This loan is secured with the pledge of the equipment.
Payments Status: On time
2018-12-01
1st payment
2018-11-30
Project implemented and in operation
The promoter has confirmed that the solar panels have been installed and that the project is operating.
2018-11-19
100% funded
2018-10-21
Open for investment
Payments Status: On time
2018-12-01
1st payment
2018-11-30
Project implemented and in operation
The promoter has confirmed that the solar panels have been installed and that the project is operating.
2018-11-19
100% funded
2018-10-21
Open for investment